重油发电机组安装施工组织设计



《重油发电机组安装施工组织设计》由会员分享,可在线阅读,更多相关《重油发电机组安装施工组织设计(20页珍藏版)》请在文档大全上搜索。
1、1 机务部分施工方案Construction Scheme for the Machinery section 1.1 主厂房行车吊装 Main building bridge crane installation 1.1.1 吊装步骤The Lifting Process1) 将履带吊开至标识位置,松钩,挂钢丝绳。Rising the crawler crane up to the mark position, loosen the hook and suspension the steel wire ropes.2) 将钢丝绳按照标识位置将固定端的行车大梁绑扎好,确保起吊时大梁平稳,必要时
2、可利用链条葫芦调平。Making the steel wire ropes in accordance with the mark position and bidding crane runaway buckstay of the fixed ends.Then keeping the buckstay rise smoothly when hanging up the crawler crane. It necessary to use the chain block with steel structure adjust the balance.3) 利用吊车将该行车大梁吊至大跑车轨道上
3、,并用钢丝绳、枕木和垫块将大梁固定平稳。Using crane hang up the crane runaway buckstay to the track of bridge motor, at the same time, using steel wire ropes, sleeper and cushion block fix and keep the crane runaway buckstay stably.4) 用同样的方法吊装扩建端的大梁和两条大梁的连接件组合体,同样放置在大跑车轨道上。Using the same way lift the buckstay of extens
4、ion ends and the connection piece unit of two buckstays then put these onto the track of bridge motor5) 将两片大梁连接组合。Conntecting and composing the two buckstays6) 将小跑车吊到大梁轨道上就位。Lifting “the small racing bike” to the track of buckstay, and it will be positioned on this track7) 将驾驶室吊至行车下。Lifting the driv
5、ing room to underside of the buckstay8) 利用卷扬机将驾驶室吊至行车大梁端头下面,并与行车连接。Using the winding engine lift the driving room below the buckstay ends, and then connects with the crane runaway9) 将行车向里拖运至合适的位置并锁定。Pulling the crane runaway inner of the structure, then find the suitable place and shock it.10) 接电源,运
6、入试吊重物,进行行车试吊。Connecting the electrical power, and try to lift the heavy.1.2 柴油发电机组吊装Generator unit installation 1.2.1 发电设备安装Generator equipment installation 工艺流程:Construction flow基础检查划线拖运轨道制作安装柴油机安装发电机安装设备中心找正设备连接二次灌浆设备中心复查Inspection to the foundationsetting outmaking and installing the track used t
7、o haul equipmentinstall diesel engine install generatorAdjusting and positioning the equipmentequipment attachmentsecondary grouting reexamining the center of equipment1.2.1.1 柴油机安装 Install diesel engineØ 基础检查、清理并复核中心线;Examining foundation, cleaning and recheck the central lineØ 按照图纸文件要求打制
8、垫铁基础,配制、安装垫铁,垫铁与基础接触密实四角无翘动。The packing iron foundation should be forged according to the drawing and files and confected and installed the packing iron.The packing iron and the base foundation should touch close-grained. Ø 设备经检查无变形等重大缺陷; Inspecting the equipments and dont find serious defects&
9、#216; 采用行车将柴油机吊装就位;Using bridge crane to position the diesel engine Ø 使用水平仪、千斤顶等调整设备,直至设备纵横中心线及轴承水平标高符合设计图纸要求;Using gradienter, jack etc.to adjust the equipment, until the center and level elevation of the equipment meet the requirement of the drawing1.2.1.2 按照以上步骤将发电机安装就位;Follow the steps abov
10、e to position the generator :1.2.1.3 柴油机与发电机设备连接;Connect the diesel engine and generator 1.2.1.4 基础二次灌浆;The basa foundation secondary grouting1.2.1.5 设备中心线及水平标高复查;Reexamine the center line and level elevation of the equipment 1.2.1.6 弹性支座安装。 Install platform1.2.2 机械辅助系统安装Install auxiliary machinery
11、system1.2.2.1 机械辅助系统主要包括辅助模块、轻质燃油系统、重质燃油系统、压缩空气系统、冷却系统、充气系统、排气系统、混油水系统、水处理系统、机房附属消防系统、燃油加热蒸汽发电系统及其他辅助系统(具体安装方法可参考润滑油系统与燃油系统的安装);Auxiliary machinery system include auxiliary modules, light fuel system, heavry fuel system, compress air system, cooling system, aeration system, exhaust system, mixing oi